The first batch of units of Zhejiang Energy Shengsi No. 2 offshore wind power project were synchronized
撰文:Lin Yue   更新时间:2021-09-26 ]

On August 14, with the completion of the on-load protection verification of the No. 3 and No. 4 main transformers of the 220kV sea booster station, the first batch of 8 wind turbines of the Zhejiang Energy Shengsi No. 2 offshore wind power filed project met the long-term synchronization.

Zhejiang Energy Shengsi No. 2 offshore wind power project is a key construction project in Zhejiang Province. The wind power filed is equipped with 63 wind turbines with a total capacity of 399.95 MW. After the project is completed and put into operation, it is expected to contribute 1.099 billion kilowatt-hours of clean energy electricity each year.
Since October 2020, the project has successively completed the commissioning of electrical units and systems, electrical handover tests, and other consulting work. Under the unified command and coordination of Energy Company, the start-up of the on-shore metering station was completed in early February 2021. In August, the sea booster station energized and other work was completed. At this point, the work of the main body of the commissioning project contract has basically ended.
The company's project department and relevant leaders carried forward the spirit of continuous struggle, meticulousness and rigor, and the courage to take responsibility, and helped the owner to successfully complete the first batch of 8 wind turbines synchronized, which won unanimous praise from all participating companies.